Relocation of the LINHARDT tool construction!

TEC.POINT Linden: The tool shop now has a new home.

The relocation of LINHARDT tool construction to the new TEC.POINT Linden has been completed. A total of 46 small and large machines were relocated within a few days. This logistical masterpiece was preceded by a long planning process.

The former Dietz building was purchased by DMW at the end of 2017. At the end of 2018 a basic cleaning and renovation followed. The hall infrastructure was modernised and expanded. In spring, sales, financial accounting and controlling moved into the 1,600 m² of office space in Linden, followed by tool construction in September and October. Currently, 3,000m² of the 4,000m² production area are occupied by the tool shop. So there is nothing to stop the future growth at the Linden location, at least in terms of space!